OAO Kaindy-Kant

The Kaindy-Kant project concerns equipment that participates in the plant heat scheme and supports stable process conditions in sugar production.

Location
Kyrgyzstan
Year
2025
Type of work
Evaporation station equipment
Project photo OAO Kaindy-Kant

2025

project year

OVC-NP

key apparatus

5.2 x 24.7

equipment size

What was done

  • Selected equipment for the production-section parameters.
  • Prepared project solutions for the OVC-NP unit and mixer.
  • Aligned delivery requirements with modernization of an operating sugar plant.

Result

  • The project formed a technical basis for section modernization with regard to plant parameters.
  • The equipment was prepared as part of an integrated production-line solution.